Site and surface preparation

To begin the preparation process, the back of each facing tile should be clean and free from loose particles with no forms of contamination evident.

The new or existing concrete, block work, substrate/timber or metal frame with the appropriate fixed substrate must be fully dried, cured and cleaned of all contaminations eg oil, grease, dirt, loosely bound materials, curing compounds, release agents, sealers etc.

If cleaning is required, ensure surface is fully dried before installing real brick facing tiles.

Limitations

  • Adhesive fixing can only be used up to 3.5m in height, internally or externally

  • Mechanical fixing must be used where brick facings exceed 3.5m in height, internally or externally. (Real Brick Rail - Mechanical fixing system coming soon - Contact us for more information)

  •  Ardex Australia Pty Ltd products are recommended for installation up to 3.5m 

  • Substrates -  Brick facings should not be adhered to Gyprock walls. The correct substrate sheets for both internal and external application need to be specified. Contact Real Brick or James Hardie for advice on the correct substrate for your application.

Installation guidelines

Step 1-  Carry out site preparation as discussed above. Mark out level lines using a spirit level.

Step 2-  Apply adhesive to the desired consistency and depth 3-4mm.

Step 3- Tiling- Adhere the Real Brick  facing tiles to the substrate from the bottom upwards. cutting in where necessary. Adhere second course using your desired bond pattern and using spacers between courses. Make sure to complete work whilst the adhesive is still workable.

Step 4-  Pointing - Once the tiling is complete you can begin pointing. You must make sure the facing tiles are dry and clean before beginning this step.  Apply the mortar between joints using a pointing tool or mortar gun (contact Real Brick for details or to hire).

Step 5- Seal-If desired, you can seal the wall once pointing is complete. Ensure the wall is dry and that all loose deposits are removed. You  can apply an appropriate sealer using a brush or roller.

While installation is relatively easy, it’s not for everyone. In this case we have a number of installers we recommend across the country. Please contact Real Brick if you would like assistance with installation.